Work continues on the wind turbine base tower section

Since the base tower section arrived at Grouse Mountain on Friday, it’s been getting a bit of a makeover. Our electricians have been busy installing cables while our millwrights have been installing more gear for the elevator that will be installed inside the tower. Tonight, the middle and top tower sections will be catching up as they travel from a lot in Surrey up to our back road off of Mountain Highway. The project site is looking different, too, as the LR1280 crane is almost completely assembled. Meanwhile, the Construction Supervisors arrived yesterday from Italy and are busy getting all the final details in place.